Park Ridge · Contract award
Purchase order increase for the Cumberland watermain replacement
AI-assisted researchHow this was researched and checkedYou are reading edition 1, an earlier version of this page. Read the current edition.
The staff memo reports the project was approved at $2,235,000 and that unforeseen conditions led to change orders and added quantities. The contractor is not named in the memo. The roll call was 7–0. Source: draft minutes.
Documented status: Amended (recorded in draft minutes), Feb 5 2024. Evidence dated . Later outcomes require a later source.
What changed, and when did it take effect?
· Amended · Recorded in draft minutes
City Council approves the purchase order increase
Meeting date: Feb 5 2024. Item VI: the motion carried (7 to 0).
p. 3 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.
p. 1 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.
What was requested, recommended, approved, contracted, reported paid and completed?
Amounts are read from the cited pages and added up by code. A recommendation, an award or an authorized amount does not establish that money was paid.
Contract value
$2,235,000
Construction
p. 1 · Staff memo of Approve a Budget Amendment and Purchase Order Increase to the Water Construction Account in the Amount of $139,000 for the Cumberland Watermain Replacement Project (Memorandum), City Council, Feb 5 2024. Open the quote and source.
Contracts, payments and completion
· Amended · Recorded in draft minutes
City Council approves the purchase order increase
Meeting date: Feb 5 2024. Item VI: the motion carried (7 to 0).
p. 3 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.
p. 1 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.
Which parcels, agencies, businesses and projects are explicitly connected?
Official identifiers and exhibit listings connect records. A name, an address or distance alone only suggests a connection.
No explicit connection is published for this item.
What remains unresolved?
Open
Several unforeseen circumstances were encountered resulting in change orders and additional quantities
Confirm dates with the City before relying on them.
p. 1 · Staff memo of Approve a Budget Amendment and Purchase Order Increase to the Water Construction Account in the Amount of $139,000 for the Cumberland Watermain Replacement Project (Memorandum), City Council, Feb 5 2024. Open the quote and source.
Open questions
No open question is recorded for this item.
What does the evidence suggest, and what would change it?
No conflicting records are published for this item.
Official source records
Editions and corrections
Each published change is a new edition. Corrections say what changed and why.
Edition 3(current)
Edition 3: 2 revised.
Edition 2Read this edition
Edition 2: 2 revised.
Edition 1(shown on this page)
First edition.