On March 20, 2024 the City Council approved, on its consent agenda, the contract for the Watermain Valve Insertion Project (PW-24-09) with Superior Excavating Company in the amount of $391,396. The bid tabulation from the opening on February 28, 2024 shows three bids, the next lowest at $476,456. The staff memo describes new valves, a hydrant and a short watermain replacement. The roll call was 5–0.

Documented status: Awarded (recorded), Mar 20 2024. Evidence dated . Later outcomes require a later source.

Official identifiers: PW-24-09

What changed, and when did it take effect?

  1. · Other · Reported by staff

    Bids opened

    Bid opening date: Feb 28 2024. Bid: $476,456 for construction; counterparty: MILLENNIUM CONTRACTING CO.

    • p. 2 · Staff memo of Approve a contract for the FY24 Watermain Valve Insertion Project, PW-24-09, to Superior Excavating Company in the amount of $391,396.00 (Memorandum), City Council, Mar 20 2024. Open the quote and source.
    • p. 2 · Staff memo of Approve a contract for the FY24 Watermain Valve Insertion Project, PW-24-09, to Superior Excavating Company in the amount of $391,396.00 (Memorandum), City Council, Mar 20 2024. Open the quote and source.
  2. · Awarded · Recorded in minutes

    City Council approves the contract

    Meeting date: Mar 20 2024. Bid PW-24-09. Contract value: $391,396 for construction; counterparty: SUPERIOR EXCAVATING COMPANY. Item VI: the motion carried (5 to 0, 2 absent). Contractor: SUPERIOR EXCAVATING COMPANY.

    • p. 3 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.
    • p. 3 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.
    • p. 3 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.
    • p. 1 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.
    • p. 3 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.

What was requested, recommended, approved, contracted, reported paid and completed?

Amounts are read from the cited pages and added up by code. A recommendation, an award or an authorized amount does not establish that money was paid.

  • Bid · Feb 28, 2024

    $476,456

    Construction

    MILLENNIUM CONTRACTING CO (bidder)
    • p. 2 · Staff memo of Approve a contract for the FY24 Watermain Valve Insertion Project, PW-24-09, to Superior Excavating Company in the amount of $391,396.00 (Memorandum), City Council, Mar 20 2024. Open the quote and source.
  • Contract value · Mar 20, 2024

    $391,396

    Construction

    SUPERIOR EXCAVATING COMPANY (contractor)
    • p. 3 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.

Contracts, payments and completion

  1. · Other · Reported by staff

    Bids opened

    Bid opening date: Feb 28 2024. Bid: $476,456 for construction; counterparty: MILLENNIUM CONTRACTING CO.

    • p. 2 · Staff memo of Approve a contract for the FY24 Watermain Valve Insertion Project, PW-24-09, to Superior Excavating Company in the amount of $391,396.00 (Memorandum), City Council, Mar 20 2024. Open the quote and source.
    • p. 2 · Staff memo of Approve a contract for the FY24 Watermain Valve Insertion Project, PW-24-09, to Superior Excavating Company in the amount of $391,396.00 (Memorandum), City Council, Mar 20 2024. Open the quote and source.
  2. · Awarded · Recorded in minutes

    City Council approves the contract

    Meeting date: Mar 20 2024. Bid PW-24-09. Contract value: $391,396 for construction; counterparty: SUPERIOR EXCAVATING COMPANY. Item VI: the motion carried (5 to 0, 2 absent). Contractor: SUPERIOR EXCAVATING COMPANY.

    • p. 3 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.
    • p. 3 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.
    • p. 3 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.
    • p. 1 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.
    • p. 3 · Approved minutes of City Council minutes, 2024-03-20, City Council, Mar 20 2024. Open the quote and source.

Which parcels, agencies, businesses and projects are explicitly connected?

Official identifiers and exhibit listings connect records. A name, an address or distance alone only suggests a connection.

What remains unresolved?

No condition or deadline is published for this item. That is a limit of the published research, not evidence that none exist.

Open questions

No open question is recorded for this item.

What does the evidence suggest, and what would change it?

No conflicting records are published for this item.

Official source records

  1. Approve a contract for the FY24 Watermain Valve Insertion Project, PW-24-09, to Superior Excavating Company in the amount of $391,396.00 (Memorandum)

    City Council, Mar 20 2024

  2. City Council minutes, 2024-03-20

    City Council, Mar 20 2024

Editions and corrections

Each published change is a new edition. Corrections say what changed and why.

  1. Edition 3(current)

    Edition 3: 4 revised.

  2. Edition 2Read this edition

    Edition 2: 4 revised.

  3. Edition 1(shown on this page)

    First edition.

Editorial responsibility: GroundSignal. Source review: . Independent research; not affiliated with a government agency.

Suggested citation: GroundSignal, “Watermain valve insertion contract with Superior Excavating,” sources reviewed 2026-09-24, source records listed on this page.

Initial permanent evidence page published September 10, 2026. Follow the dated evidence above for later additions and changes. A source-check date alone does not establish a government action or project outcome.