One green alley connects drainage work to five years of proposed owner financing

Newly reviewed minutes connect a 7–0 Council vote on the SSA final reading to a separate 7–0 Committee contract motion. The $512,851 construction award then appears on the September 21 Council agenda. Final award, completed work and individual tax bills still require separate records.

Why this connection matters

Financing approval, a construction recommendation, a final contract award and an owner’s tax bill are different milestones. Reading them together shows exactly what the City has recorded and which obligations still need parcel-level evidence.

Sources reviewed 2026-09-23. Source dates and event dates appear below.

Recommended construction contract
$512,851

Acura bid and September 8 Committee motion; final Council award, execution and payment have not been verified.

Source record [2]

Proposed abutting-owner share
50%

Staff describes an equal split with the City. The final individual charge depends on completed construction cost and parcel-level tax records.

Source record [2]

SSA financing described by staff
5 years

Staff describes five years of financing. Council approved the SSA final reading, but executed terms and annual parcel-level levies were not reviewed.

Source record [1][4]

Follow the records

  1. Source record · 2026-03-18

    Start the SSA process, not construction

    The March minutes record a 6–0 first-reading motion for SSA 26-112, covering the alley between Belle Plaine and Columbia, Washington to Harrison. Staff described a five-year financing period and a proposed first-year levy of $1.570 per $100 of equalized assessed value.

  2. Source record · 2026-08-17

    A later memo records the hearing and Committee action

    The September staff memo reports that the public hearing occurred June 15, no objection petition was filed during the following 60 days, and the Committee approved a motion on August 17 by 7–0. The memo still requests the final Council reading; these earlier steps do not establish that final outcome.

  3. Source record · 2026-08-20

    Receive bids with a separate construction price

    Six bids were opened August 20. Staff recommends Acura’s $512,851 bid. The September memo proposes a 50% City / 50% abutting-owner split and says individual costs depend on completed construction cost.

  4. Source record · 2026-09-08

    Council approves the SSA final reading, 7–0

    The September 8 Council minutes list SSA 26-112: Washington/Harrison final reading in the consent agenda and record a 7–0 roll-call approval. This supersedes the September 15 review gap about that vote; it does not supply an executed ordinance, certified parcel boundary or individual tax roll.

  5. Source record · 2026-09-08

    Committee advances construction; Council considers it separately

    Committee draft minutes record a 7–0 motion on the $512,851 Acura contract, also confirmed by the September 21 memorandum. Staff hoped construction could proceed in early to mid-October if approved; no actual start is established.

  6. Source record · 2026-09-23

    September 21 Council award outcome remains unverified

    The contract is listed on the September 21 Council consent agenda. The official archive checked September 23 had no linked minutes for that meeting. An agenda is not proof of final award, execution, payment or completion.

What the evidence does not establish

  • The final September 21 Council construction award, executed contract, payment, actual start or completion have not been verified.
  • An individual owner’s levy or tax bill and a certified legal parcel boundary have not been verified. Nearby or same-street property is not proof that a parcel owes this SSA.
  • The posted draft ordinance has an inconsistent Belle Plaine/Stewart cover label versus Washington/Harrison in the body and blank execution fields. The Council minutes resolve the vote, but an executed ordinance and parcel exhibit are still needed to resolve the document details.
  • A construction cost overrun cannot be calculated by subtracting the March $507,483 engineering-and-construction estimate from the September $512,851 construction bid. The scopes differ, and neither number is the final completed project cost.

The next records to check

Read the original sources

  1. 1.March 18, 2026 Committee of the Whole minutes

    City of Park Ridge · dated 2026-03-18 · PDF pages 2–3, Public Works A.1

  2. 2.September 8 green-alley contract recommendation and bid tabulation

    City of Park Ridge · dated 2026-09-08 · PDF page 1, funding and recommendation; page 2, August 20 bid table

  3. 3.September 8, 2026 City Council agenda

    City of Park Ridge · dated 2026-09-08 · Public Works L.2: final reading of SSA No. 26-112

  4. 4.September 8 SSA final-reading memorandum and draft ordinance

    City of Park Ridge · dated 2026-09-08 · PDF page 1, hearing and August 17 Committee action; page 2, inconsistent cover label; page 6, blank vote and approval fields. This is the posted draft, not verified enacted text.

  5. 5.September 8, 2026 Committee of the Whole agenda

    City of Park Ridge · dated 2026-09-08 · Public Works A.2: proposed $512,851 contract with Acura, Inc.

  6. 6.Park Ridge meeting archive: September 8 Council and Committee records

    City of Park Ridge · Checked September 23: September 8 Council minutes are linked; September 21 Council and Committee have agendas and recordings but no linked minutes. September 8 Committee draft minutes are attached to the September 21 Council agenda.

  7. 7.September 8 Council minutes: SSA final reading approved

    City of Park Ridge · dated 2026-09-08 · Page 2, consent agenda VI: item VIII.L.2 and the 7–0 roll-call vote.

  8. 8.September 8 Committee draft minutes: construction contract motion

    City of Park Ridge · dated 2026-09-08 · Page 2, Public Works A.2: 7–0 motion and staff hope for early to mid-October construction. Posted as draft minutes with September 21 agenda.

  9. 9.September 21 Council agenda: construction contract

    City of Park Ridge · dated 2026-09-21 · Public Works VIII.L.2: contract listed for consent; agenda does not establish the vote.

  10. 10.September 21 construction award memorandum and bid table

    City of Park Ridge · dated 2026-09-21 · Page 1 confirms the September 8 Committee 7–0 motion and requests Council award; page 2 lists all six bids.