Park Ridge · Zoning variance
Front porch and addition variances at 405 Ashland Avenue (first filing)
AI-assisted researchHow this was researched and checkedCase VA-25-07 sought variances at 405 Ashland Avenue for a front porch and a second-floor addition encroaching the front yard. Because an additional variance had been identified, the Zoning Board of Appeals continued the case at the applicants' request (vote 4–0) to March 20, 2025. Staff later reported that the same request was re-noticed under a new case number.
Documented status: Public hearing (recorded), Feb 27 2025. Evidence dated . Later outcomes require a later source.
Official identifiers: VA-25-07
What changed, and when did it take effect?
· Other · Recorded in minutes
Board continues the case
Hearing date: Feb 27 2025. Motion to continue (item IV.C). Item IV.C: the motion carried (4 to 0). Other date: Mar 20 2025.
p. 5 · Approved minutes of Zoning Board of Appeals minutes, 2025-02-27, Zoning Board of Appeals, Feb 27 2025. Open the quote and source.
p. 5 · Approved minutes of Zoning Board of Appeals minutes, 2025-02-27, Zoning Board of Appeals, Feb 27 2025. Open the quote and source.
p. 5 · Approved minutes of Zoning Board of Appeals minutes, 2025-02-27, Zoning Board of Appeals, Feb 27 2025. Open the quote and source.
p. 1 · Approved minutes of Zoning Board of Appeals minutes, 2025-02-27, Zoning Board of Appeals, Feb 27 2025. Open the quote and source.
· Public hearing · Recorded in minutes
Zoning Board of Appeals opens the public hearing
Hearing date: Feb 27 2025. Case VA-25-07. Address: 405 Ashland Avenue. Applicant: NICK HANSEN.
p. 1 · Staff memo of PUBLIC HEARING REVIEW AND ACTION: Variances at 405 Ashland Avenue - VA-25-07 (Major/Minor) (Staff Memorandum), Zoning Board of Appeals, Feb 27 2025. Open the quote and source.
p. 3 · Approved minutes of Zoning Board of Appeals minutes, 2025-02-27, Zoning Board of Appeals, Feb 27 2025. Open the quote and source.
p. 1 · Approved minutes of Zoning Board of Appeals minutes, 2025-02-27, Zoning Board of Appeals, Feb 27 2025. Open the quote and source.
What was requested, recommended, approved, contracted, reported paid and completed?
Amounts are read from the cited pages and added up by code. A recommendation, an award or an authorized amount does not establish that money was paid.
No amount is published for this item.
Contracts, payments and completion
No contract, payment or completion record is published for this item. Approval alone does not establish completion.
Which parcels, agencies, businesses and projects are explicitly connected?
Official identifiers and exhibit listings connect records. A name, an address or distance alone only suggests a connection.
No explicit connection is published for this item.
What remains unresolved?
No condition or deadline is published for this item. That is a limit of the published research, not evidence that none exist.
Open questions
No open question is recorded for this item.
What does the evidence suggest, and what would change it?
No conflicting records are published for this item.
Permits at this address since the first recorded event
No approval, award or execution is recorded, so permits are counted after the first dated event, Feb 27, 2025 (Board continues the case).
Computed by code from the building permits in the Park Ridge property release (the county permit feed), as of Nov 1, 2026. A permit shows that work was authorized, not that it was completed, and no permit recorded does not establish that nothing was built. A parcel matched by address is nominated by the address written in the record; that does not prove the record concerns it.
Matched by address: 405 Ashland Avenue
405 N Ashland AveNo permits recorded after Feb 27, 2025 through Nov 1, 2026.
Matched by address: 405 Ashland Avenue
405 N Ashland Ave5 permits recorded after Feb 27, 2025 through Nov 1, 2026: Other, New construction, Electrical, Addition; $1,059,695 in declared value; first Apr 15, 2025, last Aug 19, 2026.
Permits recorded after the decision at 405 N Ashland Ave Issued Type Work Status Declared value Aug 19, 2026 New construction UNDERGROUND SPRINKLER SYSTEM INSTALLATION Pending $9,695 May 4, 2026 Other REMOVING INTERIOR GARAGE DOOR, MINOR CONCRETE WORK Closed $30,000 Apr 27, 2026 Electrical MISC ELECTRIC Closed $5,000 Apr 15, 2026 Other FENCE Closed $15,000 Apr 15, 2025 Addition ADDITION REMODEL Closed $1,000,000
Official source records
- Zoning Board of Appeals minutes, 2025-02-27
Zoning Board of Appeals, Feb 27 2025
- PUBLIC HEARING REVIEW AND ACTION: Variances at 405 Ashland Avenue - VA-25-07 (Major/Minor) (Staff Memorandum)
Zoning Board of Appeals, Feb 27 2025