Park Ridge · Contract award

Uptown parking lot and alleys resurfacing contract

AI-assisted researchHow this was researched and checked

The City Council approved, on its consent agenda, contract PW-23-02 with Construction Management Corp. of America DBA Briggs Paving for resurfacing the Prairie Avenue parking lot, adjacent alleys and part of the Summit Avenue parking area for $267,091. Thirteen bids were opened on January 31, 2023; the next-lowest was $270,000 and the highest $360,650. Staff reported a project budget of $235,000, paid from the General Fund and reimbursed by the tax increment financing district. The consent agenda vote was 6–0.

Documented status: Awarded (recorded), Feb 21 2023. Evidence dated . Later outcomes require a later source.

Official identifiers: PW-23-02

What changed, and when did it take effect?

  1. · Other · Reported by staff

    Bids opened

    Bid opening date: Jan 31 2023. Bid: $270,000 for construction; counterparty: CHICAGOLAND PAVING CONTRACTORS. Bid: $360,650 for construction.

    • p. 1 · Staff memo of Approve the Contract for the Uptown Parking and Alleys Project, PW-23-02, with Construction Management Corp. of America DBA Briggs Paving in the amount of $267,091.00 (Memorandum), City Council, Feb 21 2023. Open the quote and source.
    • p. 2 · Staff memo of Approve the Contract for the Uptown Parking and Alleys Project, PW-23-02, with Construction Management Corp. of America DBA Briggs Paving in the amount of $267,091.00 (Memorandum), City Council, Feb 21 2023. Open the quote and source.
    • p. 2 · Staff memo of Approve the Contract for the Uptown Parking and Alleys Project, PW-23-02, with Construction Management Corp. of America DBA Briggs Paving in the amount of $267,091.00 (Memorandum), City Council, Feb 21 2023. Open the quote and source.
  2. · Awarded · Recorded in minutes

    Council approves the resurfacing contract

    Meeting date: Feb 21 2023. Item VI: the motion carried (6 to 0, 1 abstaining). Bid PW-23-02. Contract value: $267,091 for construction; counterparty: CONSTRUCTION MANAGEMENT CORP OF AMERICA. Contractor: CONSTRUCTION MANAGEMENT CORP OF AMERICA DBA BRIGGS PAVING.

    • p. 2 · Approved minutes of City Council minutes, 2023-02-21, City Council, Feb 21 2023. Open the quote and source.
    • p. 4 · Approved minutes of City Council minutes, 2023-02-21, City Council, Feb 21 2023. Open the quote and source.
    • p. 2 · Approved minutes of City Council minutes, 2023-02-21, City Council, Feb 21 2023. Open the quote and source.

What was requested, recommended, approved, contracted, reported paid and completed?

Amounts are read from the cited pages and added up by code. A recommendation, an award or an authorized amount does not establish that money was paid.

  • Budget · FY2023

    $235,000

    Construction

    • p. 1 · Staff memo of Approve the Contract for the Uptown Parking and Alleys Project, PW-23-02, with Construction Management Corp. of America DBA Briggs Paving in the amount of $267,091.00 (Memorandum), City Council, Feb 21 2023. Open the quote and source.
  • Bid · Jan 31, 2023

    $360,650

    Construction

    • p. 1 · Staff memo of Approve the Contract for the Uptown Parking and Alleys Project, PW-23-02, with Construction Management Corp. of America DBA Briggs Paving in the amount of $267,091.00 (Memorandum), City Council, Feb 21 2023. Open the quote and source.
  • Contract value · Feb 21, 2023

    $267,091

    Construction

    CONSTRUCTION MANAGEMENT CORP OF AMERICA (contractor)
    • p. 4 · Approved minutes of City Council minutes, 2023-02-21, City Council, Feb 21 2023. Open the quote and source.
  • Bid · Jan 31, 2023

    $270,000

    Construction

    CHICAGOLAND PAVING CONTRACTORS (bidder)
    • p. 2 · Staff memo of Approve the Contract for the Uptown Parking and Alleys Project, PW-23-02, with Construction Management Corp. of America DBA Briggs Paving in the amount of $267,091.00 (Memorandum), City Council, Feb 21 2023. Open the quote and source.

Contracts, payments and completion

  1. · Other · Reported by staff

    Bids opened

    Bid opening date: Jan 31 2023. Bid: $270,000 for construction; counterparty: CHICAGOLAND PAVING CONTRACTORS. Bid: $360,650 for construction.

    • p. 1 · Staff memo of Approve the Contract for the Uptown Parking and Alleys Project, PW-23-02, with Construction Management Corp. of America DBA Briggs Paving in the amount of $267,091.00 (Memorandum), City Council, Feb 21 2023. Open the quote and source.
    • p. 2 · Staff memo of Approve the Contract for the Uptown Parking and Alleys Project, PW-23-02, with Construction Management Corp. of America DBA Briggs Paving in the amount of $267,091.00 (Memorandum), City Council, Feb 21 2023. Open the quote and source.
    • p. 2 · Staff memo of Approve the Contract for the Uptown Parking and Alleys Project, PW-23-02, with Construction Management Corp. of America DBA Briggs Paving in the amount of $267,091.00 (Memorandum), City Council, Feb 21 2023. Open the quote and source.
  2. · Awarded · Recorded in minutes

    Council approves the resurfacing contract

    Meeting date: Feb 21 2023. Item VI: the motion carried (6 to 0, 1 abstaining). Bid PW-23-02. Contract value: $267,091 for construction; counterparty: CONSTRUCTION MANAGEMENT CORP OF AMERICA. Contractor: CONSTRUCTION MANAGEMENT CORP OF AMERICA DBA BRIGGS PAVING.

    • p. 2 · Approved minutes of City Council minutes, 2023-02-21, City Council, Feb 21 2023. Open the quote and source.
    • p. 4 · Approved minutes of City Council minutes, 2023-02-21, City Council, Feb 21 2023. Open the quote and source.
    • p. 2 · Approved minutes of City Council minutes, 2023-02-21, City Council, Feb 21 2023. Open the quote and source.

Which parcels, agencies, businesses and projects are explicitly connected?

Official identifiers and exhibit listings connect records. A name, an address or distance alone only suggests a connection.

What remains unresolved?

No condition or deadline is published for this item. That is a limit of the published research, not evidence that none exist.

Open questions

No open question is recorded for this item.

What does the evidence suggest, and what would change it?

No conflicting records are published for this item.

Official source records

  1. Approve the Contract for the Uptown Parking and Alleys Project, PW-23-02, with Construction Management Corp. of America DBA Briggs Paving in the amount of $267,091.00 (Memorandum)

    City Council, Feb 21 2023

  2. City Council minutes, 2023-02-21

    City Council, Feb 21 2023

Editions and corrections

Each published change is a new edition. Corrections say what changed and why.

  1. Edition 2(current)

    Edition 2: 6 revised.

  2. Edition 1Read this edition

    First edition.

Editorial responsibility: GroundSignal. Source review: . Independent research; not affiliated with a government agency.

Suggested citation: GroundSignal, “Uptown parking lot and alleys resurfacing contract,” sources reviewed 2026-09-25, source records listed on this page.

Initial permanent evidence page published September 10, 2026. Follow the dated evidence above for later additions and changes. A source-check date alone does not establish a government action or project outcome.