GroundSignal

Park Ridge · Contract award

Asphalt alley engineering contract awarded to Spaceco

AI-assisted researchHow this was researched and checked

On April 6, 2026 the City Council approved, on its consent agenda, a contract with Spaceco, Inc. for $133,300 to design and inspect the paving of five gravel alleys under the new asphalt alley program. The staff memo reports that five proposals were received and ranked by a staff team. The consent agenda vote was 7–0.

Documented status: Awarded (recorded), Apr 6 2026. Evidence dated . Later outcomes require a later source.

What changed, and when did it take effect?

  1. · Awarded · Recorded in minutes

    City Council approves the contract

    Meeting date: Apr 6 2026. Contract value: $133,300 for engineering and construction; counterparty: SPACECO INC. Consultant: SPACECO, INC.. Item VI: the motion carried (7 to 0).

    • p. 3 · Approved minutes of City Council minutes, 2026-04-06, City Council, Apr 6 2026. Open the quote and source.
    • p. 1 · Approved minutes of City Council minutes, 2026-04-06, City Council, Apr 6 2026. Open the quote and source.
    • p. 2 · Approved minutes of City Council minutes, 2026-04-06, City Council, Apr 6 2026. Open the quote and source.

What was requested, recommended, approved, contracted, reported paid and completed?

Amounts are read from the cited pages and added up by code. A recommendation, an award or an authorized amount does not establish that money was paid.

  • Contract value · Apr 6, 2026

    $133,300

    asphalt alley engineering services

    SPACECO INC (contractor)
    • p. 2 · Approved minutes of City Council minutes, 2026-04-06, City Council, Apr 6 2026. Open the quote and source.

Contracts, payments and completion

  1. · Awarded · Recorded in minutes

    City Council approves the contract

    Meeting date: Apr 6 2026. Contract value: $133,300 for engineering and construction; counterparty: SPACECO INC. Consultant: SPACECO, INC.. Item VI: the motion carried (7 to 0).

    • p. 3 · Approved minutes of City Council minutes, 2026-04-06, City Council, Apr 6 2026. Open the quote and source.
    • p. 1 · Approved minutes of City Council minutes, 2026-04-06, City Council, Apr 6 2026. Open the quote and source.
    • p. 2 · Approved minutes of City Council minutes, 2026-04-06, City Council, Apr 6 2026. Open the quote and source.

Which parcels, agencies, businesses and projects are explicitly connected?

Official identifiers and exhibit listings connect records. A name, an address or distance alone only suggests a connection.

Organizations and public bodies

What remains unresolved?

No condition or deadline is published for this item. That is a limit of the published research, not evidence that none exist.

Open questions

No open question is recorded for this item.

What does the evidence suggest, and what would change it?

No conflicting records are published for this item.

Official source records

  1. City Council minutes, 2026-04-06

    City Council, Apr 6 2026

Editions and corrections

Each published change is a new edition. Corrections say what changed and why.

  1. Edition 2(current)

    Edition 2: 2 revised.

  2. Edition 1Read this edition

    First edition.

Editorial responsibility: GroundSignal. Source review: . Independent research; not affiliated with a government agency.

Suggested citation: GroundSignal, “Asphalt alley engineering contract awarded to Spaceco,” sources reviewed 2026-09-25, source records listed on this page.

Initial permanent evidence page published September 10, 2026. Follow the dated evidence above for later additions and changes. A source-check date alone does not establish a government action or project outcome.