Ramp and plaza access open; future phases conditional · Status evidence 2026-08-14
Beach access opened; later completion and funding remain unverified
The August 14, 2026 contractor report confirms the ramp and stramp opened and fencing was removed for full beach access. Punch-list work remained; the Village separately identifies future improvements needing funding.
Next record to check: Check final pay applications and closeout for Phase Two; the September 15 archive review found no weekly report after August 14. Keep future phases conditional on funding and separate approvals.
5 source records · Kenilworth Beach and former water-treatment building. A documented decision does not by itself establish a paid amount or a completed project.