Green Bay Road resurfacing crosses municipal boundaries

Kenilworth's notice describes an IDOT corridor project extending from southern Glencoe through Winnetka into Kenilworth, with sidewalk-accessibility and pedestrian-signal proposals.

Documented status: Historical 2025 notice; current status unverified. Evidence dated . Later outcomes require a later source.

Follow the decisions

How this project got here

Read the events in order. Open a step for its evidence and connections. A scheduled action does not establish an outcome.

Ask about this project

1 events · dates retain the precision of the source

  1. IDOT project intent announced

    The page states2025 intent; it does not provide current completion evidence.

    Ask about this step

The next record to connect

Find the IDOT contract and latest completion or traffic notices before using this historical notice as current construction.

What the source records establish

Source record

IDOT announces corridor rehabilitation

The project crosses several municipal boundaries; a city-only feed can miss part of its effects.

Source record

Resurface and consider accessibility updates

Proposed scope includes milling/resurfacing, selected sidewalk improvements and pedestrian-signal updates.

Proposals and possible effects

Resurface and consider accessibility updates — read the cited record above

Possible effect

Coordinated corridor impacts

Construction could create connected access disruptions across towns; actual dates and closures need IDOT or newer municipal evidence.

Properties and geography

Green Bay Road through Glencoe, Winnetka and Kenilworth. Scope: corridor. A place or street reference is not an affected-property boundary.

Official location source

Examples on referenced streets. These links do not establish that a parcel is affected, charged, approved or eligible.

Funding and who may pay

No separate funding allocation or owner charge is established in this project's reviewed evidence. A proposal, appropriation or award does not prove payment.

Conditions and public commitments

No separate condition summary has been reviewed for this project. This is a coverage limit, not evidence that no conditions exist.

Contracts, permits and completion evidence

2025 · IDOT project intent announced

The page states2025 intent; it does not provide current completion evidence.

What changed in this edition

The permanent timeline brings the previously reviewed source records together with funding references, conditions and property context. It does not assert a new project decision or completion after the evidence dates shown above. Future material updates will identify the changed claim and its source.

Open questions and next records

  • Find the IDOT contract and latest completion or traffic notices before using this historical notice as current construction.

Official source records

  1. Green Bay Road Resurfacing notice

    Village of Kenilworth · Reviewed 2026-09-06