Winnetka decisions, commitments and what happened next.

Follow Winnetka proposals from a meeting record to funding, conditions, contracts and later evidence. This tracker explains what each reviewed source establishes and where the record is still incomplete.

Published records
4
Findings
0
County parcels
4,846
Civic source review
2026-09-06

Reviewed decisions and project status

Storage built; program phases require separate checks · Status evidence Sep 6, 2026

School and park land become stormwater storage

The west-side program links a Council-approved plan and intergovernmental agreements to storage under athletic, golf and school land.

Next record to check: Join the as-built storage and conveyance network to verified drainage areas, not a radius around the school or golf course.

Duke Childs Field, Winnetka Golf Course and Crow Island School area. A documented decision does not by itself establish a paid amount or a completed project.

Funded project; start anticipated November 2026 · Status evidence Jul 13, 2026

Willow Road reconstruction moves to November

A July update shifts expected construction to November 2026 and connects road rebuilding with storm sewer, watermain and sanitary-sewer work.

Next record to check: Check the construction notice for actual start, detours, utility interruptions and school access arrangements.

Willow Road, east of Forestway Drive to Provident Avenue; Hibbard intersection. A documented decision does not by itself establish a paid amount or a completed project.

Study and options; construction not established · Status evidence Feb 10, 2026

East Winnetka stormwater options remain a study

The Village commissioned an east-side study considering storage, conveyance, infiltration and property retrofits, with the goal of reducing flooding and improving outfall water quality.

Next record to check: Extract adopted recommendations and drainage service areas before attaching modeled benefits to properties.

Eastern Winnetka and Lake Michigan outfalls. A documented decision does not by itself establish a paid amount or a completed project.

Historical 2025 notice; current status unverified · Status evidence 2025

Green Bay Road resurfacing crosses municipal boundaries

Kenilworth's notice describes an IDOT corridor project extending from southern Glencoe through Winnetka into Kenilworth, with sidewalk-accessibility and pedestrian-signal proposals.

Next record to check: Find the IDOT contract and latest completion or traffic notices before using this historical notice as current construction.

Green Bay Road through Glencoe, Winnetka and Kenilworth. A documented decision does not by itself establish a paid amount or a completed project.

Upcoming items in reviewed sources

This edition contains no confirmed future meeting date. Check the official meeting sources below; absence here does not mean no meeting or proposal is scheduled.