A vote, a funding plan and a construction update can tell different parts of the same story. These findings connect specific records and make the remaining questions visible.

1 reviewed finding. This is a selected set of documented connections; an empty result does not mean there are no issues or public records in a town.

Public money · Park Ridge

One green alley connects drainage work to five years of proposed owner financing

The September 8 agendas separated the construction contract from proposed owner financing. Final action and individual charges remain unverified after a September 15 archive review.

Why this connection matters

A physical improvement and a property-charge boundary are different records. Following both shows which owners may bear costs and which votes must occur before treating a proposed charge as established.

Sources reviewed 2026-09-15. Source dates and event dates appear below.

Recommended construction contract
$512,851

Staff recommendation based on August 20 bids; award, execution and payment remain unverified after the September 15 review.

Source record [2]

Proposed abutting-owner share
50%

The other 50% is proposed City funding. An individual parcel bill is not calculated here.

Source record [2]

SSA financing described by staff
5 years

Proposed five-year term repeated in the September memo; enacted text and annual tax rolls remain unverified.

Source record [1][4]

Follow the records

  1. Source record · 2026-03-18

    Start the SSA process, not construction

    The March minutes record a 6–0 first-reading motion for SSA 26-112, covering the alley between Belle Plaine and Columbia, Washington to Harrison. Staff described a five-year financing period and a proposed first-year levy of $1.570 per $100 of equalized assessed value.

  2. Source record · 2026-08-17

    A later memo records the hearing and Committee action

    The September staff memo reports that the public hearing occurred June 15, no objection petition was filed during the following 60 days, and the Committee approved a motion on August 17 by 7–0. The memo still requests the final Council reading; these earlier steps do not establish that final outcome.

  3. Source record · 2026-08-20

    Receive bids with a separate construction price

    Six bids were opened August 20. Staff recommends Acura’s $512,851 bid. The September memo proposes a 50% City / 50% abutting-owner split and says individual costs depend on completed construction cost.

  4. Source record · 2026-09-08

    The September 8 outcomes still need a verified record

    September 8 has passed. The Council agenda lists the final SSA reading, while the Committee agenda lists the construction contract. On September 15, the official archive linked agendas and recordings but no minutes for either meeting. The reviewed documents do not establish the final Council action or an executed contract.

What the evidence does not establish

  • Final SSA establishment, contract award, construction completion or an individual levy/bill.
  • The legal SSA parcel boundary; nearby parcels cannot be assumed to owe a charge.
  • The executed SSA text resolving the draft cover’s Belle Plaine/Stewart label versus Washington/Harrison in the memo and body; the posted draft has blank vote and approval fields.
  • A cost overrun: March’s $507,483 estimate included engineering and construction, while September’s $512,851 is a construction bid. Those scopes are not directly comparable.

The next records to check

Read the original sources

  1. 1.March 18, 2026 Committee of the Whole minutes

    City of Park Ridge · dated 2026-03-18 · PDF pages 2–3, Public Works A.1

  2. 2.September 8 green-alley contract recommendation and bid tabulation

    City of Park Ridge · dated 2026-09-08 · PDF page 1, funding and recommendation; page 2, August 20 bid table

  3. 3.September 8, 2026 City Council agenda

    City of Park Ridge · dated 2026-09-08 · Public Works L.2: final reading of SSA No. 26-112

  4. 4.September 8 SSA final-reading memorandum and draft ordinance

    City of Park Ridge · dated 2026-09-08 · PDF page 1, hearing and August 17 Committee action; page 2, inconsistent cover label; page 6, blank vote and approval fields. This is the posted draft, not verified enacted text.

  5. 5.September 8, 2026 Committee of the Whole agenda

    City of Park Ridge · dated 2026-09-08 · Public Works A.2: proposed $512,851 contract with Acura, Inc.

  6. 6.Park Ridge meeting archive: September 8 Council and Committee records

    City of Park Ridge · September 8 Council and Committee rows link agendas and recordings; their minutes cells were blank on September 15. The September 21 rows had no agenda links at this review.

cook countyrecords

Independent research into local decisions and property records, with links to official municipal, county, state and federal sources. Not affiliated with any government. Estimates and unresolved questions are labeled. Park Ridge property release: refreshed 2026-09-07 · assessor records 2026-09-01 · Board decisions through 2026-06-09.