Wilmette · Public project evidence
School expansion could change an alley and pickup traffic
The revised Saint Francis Xavier School application combines building changes, an alley vacation, parcel consolidation and a proposed pickup/drop-off area.
Documented status: Revised application; hearing September 28. Evidence dated . Later outcomes require a later source.
What the source records establish
Source record
Several approvals are needed
Zoning requests and alley vacation are different matters; no final Village Board approval is established.
Source record
Reorganize the campus and alley
Proposal includes demolition, an addition, partial convent removal, alley vacation and a west-side pickup/drop-off area.
Proposals and possible effects
Possible effect
Local circulation may shift
An alley closure and pickup queue could change movements near adjacent properties; final access and traffic effects depend on approved plans.
Properties and geography
808 Linden Avenue; Greenleaf Avenue and 9th Street. Scope: site. Approximate campus locator averaged from four county parcels addressed 808 Linden Avenue; not a project boundary.
Official location sourceExamples on referenced streets. These links do not establish that a parcel is affected, charged, approved or eligible.
Decision timeline
Earlier hearings postponed
The page records postponements of the original Plan Commission and Appearance Review hearings.
Revised narrative submitted
New proposal retains the former convent chapel while changing other campus buildings.
Zoning hearing scheduled
The page identifies traffic, parking, trash location and lighting as hearing topics; Village Board date is undetermined.
Funding and who may pay
No separate funding allocation or owner charge is established in this project's reviewed evidence. A proposal, appropriation or award does not prove payment.
Conditions and public commitments
No separate condition summary has been reviewed for this project. This is a coverage limit, not evidence that no conditions exist.
Contracts, permits and completion evidence
A distinct contract, permit, payment or completion record has not been summarized in this edition. Approval and proposed work alone do not establish completion.
What changed in this edition
The permanent timeline brings the previously reviewed source records together with funding references, conditions and property context. It does not assert a new project decision or completion after the evidence dates shown above. Future material updates will identify the changed claim and its source.
Open questions and next records
- Check the confirmed September 28 agenda and later Zoning, Plan Commission and Village Board outcomes.
Official source records
- 808 Linden school application and meeting schedule
Village of Wilmette · Published 2026-08-21 · Reviewed 2026-09-06 · New (2026) Project Information and current meeting schedule